Progress of the Project

-Project Code :IS-UP-10-MNF - Quarter Number: 2 From: 1/5/05 To:31/7/05
-Project Title: ICTP

  1. Monitoring and following the progress of the project plane.
  2. Finalized and submission of the final project's specification booknotes to the Higher Committee of the ICTP, Cairo - EGYPT.
  3. Checked up three Servers to the MUN (Menoufiya University Network) and connected to the Network and the remaining server is under checkup.
  4. Monitoring and following with the communication Ministry for 3-Data Lines to the new network sub-branches at Sadat City. Monitoring and following the progress for the new sub-branches network that under construction at Sadat City.
  5. Opened the envelops of the offered from the companies presented to the project's infrastructure requirements and start the selection of the best one.

  1. مراقبة ومتابعة تطور العمل حسب الخطة الخاصة بالمشروع.
  2. الانتهاء وتسليم كراسة الشروط و المواصفات الخاصة بالمشروع إلي اللجنة العليا لمشروع تطوير نظم وتكنولوجيا المعلومات والاتصالات بالقاهرة - مصر .
  3. الانتهاء من فحص وتركيب وتشغيل ثلاثة خوادم بشبكة المعلومات بالجامعة والخادم الرابع تحت التجهيز.
  4. مراقبة ومتابعة توصيل ثلاث خطوط معلومات للشبكات الفرعية التي سوف يتم إنشائها بمدينة السادات مع وزارة الاتصالات والمعلومات. ومراقبة ومتابعة التطوير للتوصيلات والتجهيزات الخاصة بالشبكات الفرعية التي سوف يتم إنشائها بمدينة السادات.
  5. فتح المظاريف الخاصة بالشركات التي تقدمت بعطاءات لمتطلبات البنية الأساسية التابعة للمشروع والبدء في اختيار أحسن العروض المطابقة.