Progress of the Project

-Project Code :IS-UP-10-MNF - Quarter Number: 3 From: 1/8/05 To:31/10/05
-Project Title: ICTP

  1. Monitoring and following the progress of the project plane.
  2. The ministry of communication has finalized the connection of the Fiber Optical Cable termination up to the control room at the main site of the Information and Link Network Menoufiya University.
  3. Resubmitted the final project's specification booknotes to the Higher Committee of the ICTP, Cairo – EGYPT after we've added the recommended points mentioned by the higher committee at Cairo..
  4. Finalized the Checkup of the Four Servers to the MUN (Menoufiya University Network) and connected them in the control room of the Information and Link Network at the main Site and the they are working in good and stable condition.
  5. Finalized the connection of the three Data Lines to the new networks and sub-branches that will be establish at Sadat City with the communication Ministry.

  1. مراقبة ومتابعة تطور العمل حسب الخطة الخاصة بالمشروع.
  2. وزارة الاتصالات انتهت من توصيل وصلة نهاية كابل أوبتكل الفيبر حتى حجرة التحكم بالموقع الرئيسي بشبكة الربط والمعلومات, جامعة المنوفية.
  3. > الانتهاء وتسليم كراسة الشروط و المواصفات الخاصة بالمشروع إلي اللجنة العليا لمشروع تطوير نظم وتكنولوجيا المعلومات والاتصالات بالقاهرة - مصر . بعد إضافة النقاط التي أوصت بإضافتها اللجنة العليا بالقاهرة.
  4. الانتهاء من فحص وتركيب وتشغيل أربعة خوادم بشبكة جامعة المنوفية بحجرة التحكم بالموقع الرئيسي وهي تعمل بحالة جيدة ومستقرة.
  5. الانتهاء من توصيل ثلاث خطوط معلومات للشبكات والفروع الفرعية الجديدة التي سوف يتم إنشائها بمدينة السادات مع وزارة الاتصالات.