- Monitoring and following the progress of the project plane.
- Finished the connection of ninety nine (99) end points ( i.e. the connection to the Internet) at the main Building (I) and the main Building (II) within the Minufiya University side at Shebin El-Kom and will continue the connection for the remaining twenty one (21) end points (i.e. the connection to the Internet) to reach the total number of one hundred twenty (120) end points.
- Finished the connection of eighty (80) end points (i.e. the connection to the Internet ) at the Sadat City side new five sub-networks ( Faculties of (Law, Commerce, Education) Studies and Environmental Research Institute, and General Public Service Center) which will establish at Sadat City.
- The awarded company handled most of the items included the contract.
- The investigation and checkup the imported
items will take place in the first week of May.
|